0 like 0 dislike
3 views
by

How Does Sap Calculate Work In Process (wip) In Product Cost By Order?

1 Answer

0 like 0 dislike
by

The system first runs through all the production order for the month and checks for the status of each production order. If the status of the production order is REL (Released) or PREL (Partially released) and if costs are incurred for that order system calculates WIP for the production order.

The system cancels the WIP for the production order when the status of the order becomes DLV (delivered) or TECO (Technically complete).

Welcome to NETRAANSWERS.COM, where you can ask questions and receive answers from other members of the community.
...